Friday, September 24, 2010

A Visit to Dawson



Mr. Lazes and Tom Murray flew in from Charlotte to review the new beach area plans architect Ole' Sondresen completed this week.  Tom is an experienced real estate marketer specializing in projects like Dawson Lake.

Bob Chamberland and his building construction crew were busy this week installing the West Virginia grown Eastern Hemlock siding on the spec home.  Eastern Hemlock has been used for construction of homes and barns in WV for over 200 hundred years and is resistant to decay and weathers to a pleasingly warm color.

- Richard Grist




Friday, September 17, 2010

The Shift of Seasons at Dawson


As summer winds down, the construction at Dawson Lake is still moving along.  The weather has been exceptional for Bob Chamberland and his construction crews to stay busy.

 With a few more days of fill work, the Hilltop road will be completed and ready for stone and hydroseeding.

The survey crew from Terradon continues to provide assistance when called upon.

Architect Ole' Sondresen met on site with Mr. Lazes, Bob Chamberland and Paul Grist to site the new spec home to be built on the lakefront.  This home is to be built with leading edge "Green" technology and will serve as a model for the possibilities future homeowners could include in the design of their homes at Dawson Lake.

If the Indian Summer continues this fall, construction of the pool and beach cabana will get underway and the amazing spec home on Memory Lane will be completed.

The cool nights create early morning mist on Dawson Lake and the leaves are just starting to turn and this should be a very colorful year.

- Richard Grist






Thursday, August 26, 2010

Architecture Comes to Life at Dawson

Work on the spec home continues and it is exciting to see the Ole' Sondresen's architectural design come to life.  The outdoor living area adjacent to the kitchen is well underway with some very nice Elderman Spruce beams from White Pine Milling in Racine WV being installed for the rafters.

The new well has been drilled by Tuckwiller Well Drilling and the grade around the home has been raised to finish level.

The windows and doors are installed and the kitchen cabinets are ready to install soon.

- Richard Grist








Tuesday, July 20, 2010

Taking Time to Smell the Flowers

With the construction phase in full swing, it is sometimes nice to take a walk around the project and experience the progress from a little different perspective.

The din of the construction gives way to wildflowers, wood ducks, clouds, sunbeams, spider webs, bird songs and lake reflections.

- Richard Grist







Friday, July 16, 2010

Ducks on the Pond - July 2010

Bob Chamberland and his four crews had some time down this week as tremendous thunderstorms moved across the region and delayed some of the road work. However, the much needed rain continued filling of the lake, which by the way has several wood duck hens with their newly hatched chicks.

The Lakeview West road is just about completed with just the big fill in progress.  The crossing of the deep hollow on the southern terminus of the road will require thousands of yards of fill to bring it to final grade and this work will be ongoing for a few more days.

Terradon Engineering completed the grade staking and the grubbing and clearing of Tip Top Lane, the last road slated for this phase of the development,  was started this week.  It will require a substantial cut to get to final grade but will access some of the nicest views on the property. Road construction superintendent, Richard Persinger is using the ideal shale/rock material from this cut to fill in  the deep crossing on Lakeview West.

The conduit crew is making steady progress and started laying the underground conduit along Lakeview West this week and the chipping crew is getting along well, with most of the area on the eastern side of the lake completed.
 
- Richard Grist