Monday, July 20, 2009

Dawson Lake Progress : July 20, 2009

Here are a few pictures of the great progress being made at Dawson Lake by Bob Chamberland & Crew. The rain has abated and the weather is just right for dam building.

The keyway for the dam is just about finished and the dam will start to rise. The internal workings of the dam (sand, limestone, culverts etc Will be installed as the dam is built.

The power cable is being pulled through the underground conduit that Bob installed last fall by the Power Company with a crew out of VA.

The hydoseeding that was done last fall is really taking hold and the road banks are looking great.

- Richard Grist







No comments:

Post a Comment