Dawson Lake Progress : May 8, 2010 : The "Big Dig"

The first week of May brought sunshine and excellent working weather and Bob's road crew made great progress fixing the slips and rebuilding the road at the top of the mountain. A rock hammer was brought in to bring the last section of road to finished grade.

Bob's spec home construction crew finished laying the foundation block and laid down the subfloor. Next week the walls will be going up and architect Ole' Sondresen will be coming in from New York. Ole' will be onsite to finalize the plans for the beach cabana and swimming pool.

The grass that was hydroseeded last week is sprouting and things are really starting to green up around the lake area.